of Ltd. "Tukuma Siltums" in Tukums was officially opened in January. Flue gas condensers with a capacity of 10MW, is now the largest in Latvia. The energy produced by condensing process reaches 15 to 25% of boiler capacity. Flue gas condensers works as a treatment plant, especially in boilers where the fuel is used by bio-fuels. During the implementation of project a new automatic control system was installed of the existing water heating boilers, as well as a new pipeline system was built up. The total project cost - LVL 2,613,297, -